Time-Current Curves with Excel IV

This is the final part of the tutorial creating for time-current current curves with Excel. We shall be able to attain a complete relay coordination similar to this following curve.

Complete Time Current Curve

To understand better the coordination curve, here are the parameters. Please note that values are referred to the primary which is 11kV.

Utility Supply (0.2 time multiplier)
Voltage : 11kV
SC Capacity : 75MVA
Protection: 250A set @ 5IN
Supply Cable
Size : 35 mm2 PVC/PVC
Primary Circuit Breaker (0.16 time multiplier)
Rating : 160A
Setting 1 : 800A @ 5IN
Setting 2 : 1120A @ 7IN
Power Transformer
Rating: 2500 kVA, 11/0.415kV, 6.25%Z
Secondary Circuit Breaker (0.12 time multiplier)
Rating : 4000A (150A - referred to Primary)
Setting 1 : 604A @ 4IN
Setting 2 : 905A @ 6IN
Motor Cable
Size : 185 mm2 PVC/PVC
Motor Circuit Breaker (0.1 time multiplier)
Rating : 800A (30A - referred to Primary)
Setting 1 : 483A @ 16IN
Setting 2 : 604A @ 20IN

The utility time multiplier is normally provided by the power provider. Then, we need to work below it else, our protection is not time coordinated with the utility.

For the motor circuit breaker, we need to select a setting wherein the value protection will not trip during motor starting which is ideally 6 time the full load motor current and it should still be tripping below the secondary circuit breaker setting.

You may have noticed that I have included the damaged curve of the cables. These are correctly selected because they way above the protection setting of the utility.

This is the final part of the time-current curve with excel. If you have any queries, feel free to post a comment and we shall discuss.

 

Our Sponsors

Design Stages

Successful projects were not developed overnight. They have undergone through several stages. Missing any one stage may have caused disastrous effect on the projects causing failure.

Conceptual Design
To develop your project ideas into a more tangible perspective.
Front End Engineering and Design (FEED)
To explore possibilities to enable better control on the outcome of ideas, getting the final result without delay but more importantly without overshooting your budget.
All ideas need to be developed at this stage of the project.
Detail Design
The final stage of the design aspect of your project. Only minor, unforeseen and uncontrollable by the project team need to be implemented at this stage.
Injecting radical changes at this stage could mean redevelopment of the project concepts leading to project delays and budget overshoot.

We could offer the Electrical Engineering aspect of your project ideas. If you want to seek our help, contact us at HELP@FILIPINOENGINEER.